Thornton ES Interior Renovations

San Antonio
August 2014

This fast-track renovation project at Thornton Elementary School transformed existing classrooms into a new music room, instrument storage, and a small general classroom. The scope also included upgrades to the platform room and theatrical stage to support performance and instructional needs.

Work involved selective demolition, carpentry, drywall, drop ceilings, flooring, specialties, HVAC, plumbing, electrical, fire sprinkler, and fire alarm systems. All renovations were completed within 60 days of notice to proceed.

Market

K-12

Architect/Engineer

Pfluger Architects

Type

Renovation

Size

3,383 sf

Owner

Northside ISD

Thornton ES Interior Renovations

San Antonio
August 2014

This fast-track renovation project at Thornton Elementary School transformed existing classrooms into a new music room, instrument storage, and a small general classroom. The scope also included upgrades to the platform room and theatrical stage to support performance and instructional needs.

Work involved selective demolition, carpentry, drywall, drop ceilings, flooring, specialties, HVAC, plumbing, electrical, fire sprinkler, and fire alarm systems. All renovations were completed within 60 days of notice to proceed.

Market

K-12

Architect/Engineer

Pfluger Architects

Type

Renovation

Size

3,383 sf

GET A QUOTE

We’re glad you found us! At CGC General Contractors, we’re here to support you—whether you’re starting a new project, looking for expert guidance, or just have a question. Send us a message and we’ll get back to you soon.